2021 Street Improvement Project Underway
- Linn Drive from Hanover to Pitt (Milling on September 15, Paving on September 16)
- Acre Drive from Linn to the cul de sac (Milling on September 15, Paving on September 16)
- Strawberry Court from Acre to boundary (Milling on September 15, Paving on September 16)
- Sadler Drive from Garland to Biddle (Milling on September 14, Paving on September 16)
- Sadler Court (Milling on September 14, Paving on September 16)
- Garland Drive from Ridge to Rockledge (1/2 width to adjoin paving done last year by UGI) (Milling on September 14, Paving on September 15 and 16)
- Glendale Street from Walnut to Hillside (Milling on September 13, Paving on September 14 and 15)
- Walnut Street at intersection with Orange
- Sutton from Sherwood intersection and adjoining road segments (Milling on September 13, Paving on September 15)
- Samuels Drive/Giant Lane from Spring Garden to driveway at Seven Gables Park (Milling on September 10, Paving on September 13 and 14)
- Pomfret Street Parking Lot (Milling on September 10, Paving on September 13)
UTBWC will be performed on the following streets beginning Wednesday, September 22.
- South Street/Orange Street from Hillside Drive to the intersection of South/Orange
- Georgetown Circle
- White Birch from Orange Street to Georgetown Circle.