Milling & Paving Set to Begin Week of October 7

CURRENT SCHEDULE AS OF 10/10

Tuesday, October 8: Mill Lincoln and G Streets
Wednesday, October 9: Mill Orange Street and Mooreland Avenue
Thursday, October 10: Mill West Street and Penrose Place
Friday, October 11: Finish milling Penrose Place, Pave Lincoln and G Streets
Monday, October 14: Pave Orange Street and Mooreland Avenue
Tuesday, October 15: Pave West Street and Penrose Place

Milling and paving will begin Monday, October 7, as part of the Borough’s Street Improvement Program. Because the milling and paving phases of the project cannot be combined, there will be a period of time when the milled road is reopened to traffic. Motorists and pedestrians will need to use extra caution when traversing manhole lids, water & gas valve lid boxes, driveway ramps, curb cuts, and storm inlets because there features will temporarily be sticking up higher than the road surface. We will work with the contractor to minimize the time the road stays in this condition.

It may be necessary to prohibit parking in the area at various times during the work. Please follow all signs and traffic control measures and personnel during the work.

Here is the schedule, weather permitting:

Monday, October 7: Mill Lincoln and G Streets
Tuesday, October 8: Mill Orange Street and Mooreland Avenue
Wednesday, October 9: Mill West Street and Penrose Place; Begin paving Lincoln and G Streets
Thursday, October 10 and Friday, October 11: Continue Paving Orange Street, Mooreland Avenue, West Street, and Penrose Place
Monday, October 14 & Tuesday, October 15: Continue/Complete paving if necessary