UGI Restoration Work

Beginning Monday, May 13, crews will begin repaving North College Street between A Street and West Penn Street. We will provide a more detailed schedule in the following days.

UGI's paving contractor will be performing patch work in several areas. Below is a tentative schedule

Monday, 5/13
Sections of:
Walnut Bottom Road
Marsh Drive
Walnut Street
West Willow Street
South Hanover Street

Tuesday, 5/14
249 8th Avenue

Wednesday, 5/15
Sections of:
Fairview Road
Cavalry Road
East North Street

Thursday, 5/16
Sections of :
North Pitt Street
West Louther Street
North Bedford Street

Friday, 5/17
Sections of:
Otto Avenue
East High Street